A typical kitchen remodel sequence
Every job is different, but most kitchen remodels follow roughly this order. Durations are working days for a mid-size kitchen with one crew per trade:
- Permit: 5 days (varies a lot by town)
- Demo: 2 days
- Rough plumbing and rough electrical: 2 days each, often overlapping
- Rough-in inspection: 1 day
- Insulation and drywall: 4 days
- Cabinets: 3 days
- Countertop template, then install: about 1 day each with fabrication time between
- Backsplash tile: 2 days
- Finish plumbing and electrical: 1 day each
- Paint and touch-up: 2 days
- Final inspection and punch list: 1–2 days
Make the template yours
Change durations to match your crews, add the steps your town requires, and save it. Next job, pick the template and a start date: every date fills in, and the job is ready to share with your crew, subs and client the same day.
Common questions
Can I download a template as Excel?
Yes. Any schedule in Construction Company Software exports to Excel, CSV, Microsoft Project XML, Primavera P6 XER, or a calendar file.
Can I build a template from a past job?
Yes. Save any project's schedule as a template; dates are stripped and the task order, durations and links are kept.