Troubleshooting
Troubleshooting: failed or odd schedule imports
Why an import fails or looks wrong — wrong file type, missing links, shifted dates, odd durations — and how to fix each.
The import fails outright
- “No tasks were found in this file” — the file is empty, it's the wrong sheet, or the task name column isn't recognised. In Excel, put the task list on the first sheet with a header row (Name, Duration, Start, Predecessors).
- .mpp file rejected — save from Microsoft Project as XML (File → Save As → XML Format) and import that.
- P6 export rejected — export as XER (or P6 XML), not PDF or Excel layout.
- File too large or times out — split very large programs by project, or remove resource and cost tables before exporting.
Warnings in the preview and what they mean
- “N link(s) pointed at missing tasks… were skipped” — the predecessor was outside the exported range or filtered out. Re-export with all tasks, or add the links after import.
- “link(s) to other projects were skipped” (P6) — cross-project links can't come across. Add a milestone for the outside date and link to that.
- “Percent lag … converted to 0 days” (Microsoft Project) — lag stated as a % isn't supported. Fix the lag in the preview or after import.
- “Level-of-effort/WBS summary … imported as a regular task” (P6) — check its duration after import or delete it.
- “predecessor reference(s) didn't match a task” (Excel/CSV) — predecessors must be row numbers or IDs from the same file, like 3, 3FS+2 or 3SS.
- “Columns not imported: …” — those columns aren't mapped. Rename them to Name, Duration, Start, Finish, Predecessors, Trade or Notes.
- “row(s) had formatting problems” — usually a stray quote or line break inside a cell. Save as CSV UTF-8 and try again.
- “The file has several projects; importing …” — only the first project is imported. Export one project per file.
Dates look shifted
- Your work calendar differs from the source. Construction Company Software recalculates with the project's calendar — if the source worked Saturdays, set up a 6-day calendar in Settings → Work calendars before importing.
- Day and month swapped (03/04 read as March 4 instead of 3 April): use YYYY-MM-DD dates in Excel or set your sheet's date format before saving as CSV.
- Tasks all start on the project start date: there were no links in the file. Leave start dates in, or add links after import.
- Constraints from the source (must start on, start no earlier than) are kept and can pin tasks. Check the constraint column on tasks that won't move.
Durations look wrong
- Durations are working days. “2w” is read as 10 days, and durations stored in hours are converted to working days.
- Milestones must have 0 duration — anything with a duration imports as a task.
Undo a bad import
Every import is saved as a schedule change. Open Baselines & versions and restore the version from before the import, or delete the imported tasks and import again. Deleted tasks can also be restored from Settings → Recycle bin for 30 days.
Still stuck? Search the help center or check the service status.